wiki:supportSchedule

Version 48 (modified by Paul Leo, 3 years ago) (diff)

--

Support Schedule (Paul's Schedule)

This page provides the adopter support schedule. The intent is to provide adopters visibility to Paul's work load and to communicate priorities and available hours/funding. Please visit the Development Schedule for information about where the development is headed.

Montana
Prioritized Tasks:

  1. Work with MT IT to get db up for ibisph-admin
  2. Work with MY IT to get a dev instance of ibisph-view working
  3. BRFSS is the next step.

Funding: Use 2016 and 2017 Support funding.
Expected Due Date: TBD.

New Jersey
Prioritized Tasks:

  1. Work on map layers for NJ (10 days)
  2. Working with Paul N. and Garth about deployment (3 days)
  3. Garth updates UI (5 days)

Funding: Current 2016 support contract.
Expected Due Date: TBD.

NM EPHT
Prioritized Tasks:

  1. update and New NCDM indicators (2 - 3 months)
  2. implement the infrastructure that would allow EPHT to update their site w/o IT intervention (TBD)
  3. Static pages - output from EDAC content management system - if assitance is needed

Funding: Current 2016 support contract.
Expected Due Date: TBD

NM
Prioritized Tasks:

  1. ongoing updates to site
  2. implementing and testing 2.4/3.0 changes to db

Funding: Current 2016 support contract.
Expected Due Date: TBD

Kentucky EPHT
Prioritized Tasks:

  1. Work on prioritizing next steps.

Funding: Current 2016 support contract.
Expected Due Date: TBD

Hawaii
Prioritized Tasks:

  1. Work on implementing YRBS queries (1 month).
  2. New Map layers
  3. Documentation of Hawaii IBIS site - (description of IBIS, components, where to obitain, install, configuration, etc)

Funding:2016
Expected Due Date: 8/31/2016

Kentucky Injury EPI
Prioritized Tasks:

  1. Finish implementation of IBIS 2.3 on new server. (14 days)

Funding: Current 2016 support contract.
Expected Due Date:TBD

Maryland
Prioritized Tasks:

  1. Initial Setup

Funding:
Expected Due Date:TBD

Utah
Prioritized Tasks:

  1. UT EPHT UI tweaks, including reverse color map, changing legend
  2. Moving toward 3.0

Funding:
Expected Due Date:TBD