Changes between Version 66 and Version 67 of supportSchedule


Ignore:
Timestamp:
03/13/17 12:22:45 (5 years ago)
Author:
Paul Leo
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • supportSchedule

    v66 v67  
    33This page provides the adopter support schedule.  The intent is to provide adopters visibility to Paul's work load and to communicate priorities and available hours/funding.  Please visit the [wiki:developmentSchedule Development Schedule] for information about where the development is headed.
    44
    5 '''IBISPH-COP'''[[br]]
    6 1. Test and Verify new SVN and Trac VM, includes documentation for users (all IBIS adopters) (1-2 weeks)
    7 Funding: fractional charges to IBIS adopters
    8 Expected Due Date:~2/14/2017
    95
    106'''Montana''' [[br]]
    117Prioritized Tasks:
    12  1. Work with MT IT to get a dev instance of ibisph-view working (1 week)
    13  1. PCO Indicator and community reports (2-3 months) - Due Date 3/31/2017
    14  1. Refine Hospital Discharge Queries (1-3 weeks)
    15  1. Begin work on Emergency Room Discharge Queries (1-3 weeks)
     8 1. PCO Indicator and community reports (1 month) - Due Date 4/30/2017
     9 1. Begin work on Emergency Room Discharge Queries (1-3 weeks) ?
    1610
    1711Funding: Use 2017 Support funding.  [[br]]
     
    2014'''New Jersey'''[[br]]
    2115Prioritized Tasks:
    22  1. Bring up Local Dev environment using Glassfish App Server for IBIS v 2.3 (1-3 days)
    23  1. Clean up ibisph-admin v 2.3 DB (1-2 days) 1/25/2017
     16 1. Update and Migrate ibisph-admin to different machine (1-2 days) 4/15/2017
    2417
    2518Funding: Current 2016-2017 support contract.[[br]]
     
    2821'''NM EPHT'''[[br]]
    2922Prioritized Tasks:
    30  1. update pages as needed
     23 1. update content pages as needed
    3124 1. update and New NCDM indicators (2 - 3 months)
    32 Funding: Current 2016 support contract.[[br]]
     25Funding: Current 2016-2017 support contract.[[br]]
    3326Expected Due Date: TBD
    3427
     
    3831 1. implementing and testing 3.0 changes to db
    3932
    40 Funding: Current 2016 support contract.[[br]]
     33Funding: Current 2016-2017 support contract.[[br]]
    4134Expected Due Date: TBD
    4235
    4336'''Kentucky EPHT'''[[br]]
    4437Prioritized Tasks:
    45  1. Implement Indicator and Community Reports (TBD)
    46 Funding: Current 2016 support contract.[[br]]
     381. Implement ibisph-admin  (4/1/2017)
     391. Implement Indicator and Community Reports (5/31/2017)
     40Funding: Current 2016 - 2017 support contract.[[br]]
    4741Expected Due Date: TBD
    4842
     
    5044Prioritized Tasks:
    5145
     46 1. Prams Queries - perhaps using SAS to create XML files (1-2 weeks)
     47 1. Begin work on Vital Records Queries.(1-2 months)
    5248 1. New Map layers (2 weeks)
    53  1. Prams Queries - perhaps using SAS to create XML files (1-4 weeks)
    54  1. Begin work on Vital Records Queries.(1-2 months)
    5549
    56 Funding:2016 maintenance support contract (ending 6/30/2017) [[br]]
     50Funding:2016 - 2017 maintenance support contract (ending 6/30/2017) [[br]]
    5751Expected Due Date: 6/1/2017[[br]]
    5852
     
    6155 1. UT EPHT UI tweaks, including reverse color map, changing legend, new maps because Local Health District change in 2015
    6256Funding:[[br]]
    63 Expected Due Date:TBD
     57Expected Due Date:4/1/2017
    6458
    6559'''USET'''[[br]]
     
    6963 
    7064Funding:2016 Maintenance support contract[[br]]
    71 Expected Due Date:2/14/2017
     65Expected Due Date:3/31/2017