    66'''3rd Round of Testing, full NM data migration to production: End of 2019?'''
    77
    8 Version 3 does not provide any major features.  This is an admin backend data release and basic view app conversion to the new structure and latest dependent libraries.  The schedule aligns with NM availability which will provide the time needed to go through and scrutinize all page types, polish the user interface, and perform the data migration from 2.3 to the new data structure.
     8Version 3 is mainly an admin backend data release and basic view app conversion to the new structure and latest dependent libraries.  The schedule aligns with NM availability which will provide the time needed to go through and scrutinize all page types, polish the user interface, and perform the data migration from 2.3 to the new data structure.
    99See [wiki:designGoals 3.0 Design Goals] for information about what version 3.0 is trying to accomplish (See [wiki:currentDesign Current Design Thoughts] for current ideas).
    10 
    11 Breakdown Once NM End User Testing Begins:
    12 - 1w - Walk through all major page types.  This includes analyzing web statistics, cost to maintain, information that can be better communicated, user interface, page layouts etc.
    13 - 4w - Implement UI findings.
    14 - 1w - Final round of SQL script and data mods
    15 - 4w - Query system updates for integrated indicator and query result data structure.  This effort includes data sources and general cleanup.  It will likely include minor Java, kendo and leaflet tweaks as needed.
    16 - 1w - Final Admin App UI updates.  This includes a scrutinization session.
    17 - 1w - View app IP updates
    18 - 1w - View app CP updates
    19 - 1w - Test and clean up UI, CSS, XSLT code (hardening).
    20 - 1w - Working with Lois and Paul help/implementing nm
    21 ==> 17 weeks ==> 5 months with time off and adopter support.